Neat Cement Punning

 

Here is how to become a Concrete Calculator by yourself for different types of concrete operation like concrete floor , plaster wall , ceiling plaster, cement finishing etc. works.

1) Artificial Stone Flooring ===>

The Quantity of materials required for 100 Sq.m. 25mm Thick Artificial Stone Flooring 3mm Topping is

Cement @ 0.859 or 25 Bags
Sand @ 0.97 cu.m or 28 Bags
Stone Chips (6mm and Down) @ 1.94 cu.m or 56 Bags

2) Cement and Sand Plastering===>

For 100 Sq.m Of Plastering the required Quantity Of Materials are :
With Cement Mortar (1:6) :-
12mm thick ——–    Cement = 0.274 cu.m or 8 Bags             Sand = 1.64 cu.m. or 48 Bags
15mm thick ——–    Cement = 0.342 cu.m. or 10 Bags          Sand = 2.05 cu.m. or 59 Bags
20mm thick ——–    Cement = 0.456 cu.m. or 13 Bags          Sand = 2.74 cu.m. or 79 Bags
With Cement Mortar (1:4) :-
10mm thick ——–    Cement = 0.319 cu.m. or 9 Bags            Sand = 1.29 cu.m. or 37 Bags
6mm thick  ———   Cement = 0.192 cu.m. or 6 Bags             Sand = 0.77 cu.m. 22 Bags

3) Neat Cement Punning===>

Quantity Of Materials Required for 100 Sq.m. Of Neat Cement Punning is as follows:-
1.5mm Thick ——-    Cement = 0.186 cu.m. or 5.5 Bags
3mm Thick    ——-    Cement = 0.375 cu.m. or 11 Bags
6mm Thick    ——-    Cement = 0.750 cu.m. or 22 Bags